The Unanswered Question Regarding A Correct Property Description In A Mechanic's Lien Against A Condominium - Cordeck v. Construction Systems, Inc. II - Part 1

Back in April of 2008 we wrote about a lengthy opinion delivered by the 1st District Appellate Court concerning a mechanic’s lien dispute over the property shown below:


View Larger Map

Since the Appellate Court delivered that opinion some of the parties were apparently able to settle their disputes and some of the parties found new issues to appeal. On September 9, 2009, the Court issued a second appellate opinion in this matter addressing several issues surrounding mechanic’s liens. Over the next few days, we will be addressing these decisions.

The full set of facts is available in the opinions. In short, Cordeck was subcontracted to Construction Systems, Inc. (CSI) to supply and install structural steel for a condominium project in Chicago. On January 23, 2003, Cordeck filed this lien stating it was owed $1,003,489.70 for work on the project and filed suit to foreclose on that lien in April 2003. In August of 2003, the condominium declaration was filed (if you want to read it, you’ll have to go to the Cook Count Recorder of Deeds office – it’s document 0324110024). On September 25, 2003, CSI filed this lien claiming it was due $1,979,412.00 and filed an answer and amended counterclaim in the Cordeck case alleging as much.

A bank holding a mortgage on the property, First Midwest Bank (FMB) challenged the validity of the liens filed by both Cordeck and CSI, the challenges and the Court’s decisions are the subject of our posts on this case.

The first challenge raised by FMB to the lien filed by CSI was that the lien failed to sufficiently describe the property encumbered by the lien. Here is the appellate brief filed, you will see that it contains arguments regarding the sufficiency of the description under Section 7 of the mechanic’s lien act, but also that it asks the court to consider the issue of Section 9.1 of the Illinois Condominium Property Act which arguably requires apportionment of a mechanic’s lien on a condominium property once a unit has been conveyed to a purchaser.

Here are the briefs in response to the appellate brief and the reply brief filed. You will see that the argument made in contravention of applying the apportionment rule of 9.1 centers around the fact that no unit had yet been transferred to a purchaser when CSI filed its lien and arguably then, CSI was not required to apportion the lien.

The reason we’re attaching the briefs and discussing the argument is that the appellate opinion didn’t address the issue. While we don’t know why the Court did not want to finally wade into the waters of Section 9.1, we can see from the briefs that a decent argument was advanced in contravention of applying the apportionment requirement to the CSI lien which may be the reason it wasn’t included in the opinion.

FMB also argued that even if Section 9.1 did not apply, the fact that a more recent and particular property description had been filed prior the recording of the CSI lien meant that the CSI lien was invalid if it did not include the most recent and more particular description. The Court addressed the description included in the CSI lien in accordance with the terms of Section 7(a) which requires that the claim for lien include:

a sufficiently correct description of the lot, lots or tracts of land to identify the same”

The court found that the description of the CSI lien met the requirement that “the description be sufficient to identify the affected land” – adequate under the standard of the Act – and rejected the request to invalidate the lien on the basis of the description.

As you can see from the lien, it used the plat of survey description, included the common address of the property and also had the property identification numbers for the parcels that had existed prior to the apparent merger of the property into a different number. It is also interesting that there was testimony from an employee of the recorder’s office who testified that a lien recorded on the property as a whole would appear in a search of the chain of title of each unit included in the condominium declaration. (This is perhaps true of searching at the actual recorder’s office, but searching online with the PINs for the condominium units shows none of the liens filed by Cordeck or CSI. The first condominium unit PIN can be found on this map from the Assessor’s Office).

There are more than a few parties that would have appreciated a discussion of the application of Section 9.1, but the facts appear to have been against the treatment of the issue. For now, we have another case that offers some welcome guidance regarding the sufficiency of a property description under the Act. 

Tomorrow we will discuss the issue of timeliness in filing the lien raised in this case.

Trackbacks (0) Links to blogs that reference this article Trackback URL
http://www.illinoisconstructionlawblog.com/admin/trackback/156235
Comments (0) Read through and enter the discussion with the form at the end
Post A Comment / Question Use this form to add a comment to this entry.







Remember personal info?
Send To A Friend Use this form to send this entry to a friend via email.