Indiana Supreme Court Unequivocally Endorses The Economic Loss Doctrine
Economic losses concern defeated or diminished expectation interests arising out of inadequate or failed contractual performance, which involve neither personal injury nor physical damage to other property. The Economic Loss Doctrine provides that purely economic losses, originating out of and concerning contractual performance, are addressable, if at all, under contract principles. Conversely, economic losses are not recoverable in tort, given that none of its safety-protection interests are implicated by such disputes.
The Indiana Supreme Court recently affirmed this tenet in a landmark ruling, which upheld the trial and appellate courts preclusion of tort recovery against design professionals by a project owner for damages associated with alleged design and construction defects.
On June 29, 2010 the Indiana Supreme Court issued its opinion in Indianapolis-Marion County Public Library v. Charlier Clark & Linard, P.C., 2010 WL 2594314 (Ind.). This dispute arose from the renovation and expansion of a library and parking garage. The Library directly entered into contracts with the architect and general contractor for the project. The project architect, in turn, subcontracted for services with various design professional consultants.
The Library asserted negligence claims against some subcontractors and the architect’s structural engineer, seeking recovery for construction and design defects in its renovated and expanded facilities. The trial court dismissed the negligence actions based on the Economic Loss Doctrine, with the state’s court of appeals affirming. Indiana’s endorsement of the Economic Loss Doctrine in Indianapolis-Marion County Public Library eliminated any doubt as to its application to design professionals given the authoritative nature of the Court’s opinion.
In justifying the application of the Economic Loss Doctrine to this design/construction dispute, the Court reasoned that the Library established the expectations of the parties by entering into various contracts. If recovery in tort were permitted, the Library could effectively circumvent the bargained-for exclusions and risk allocation outlined in the governing contracts. The Court, citing Chief Judge Cardozo’s seminal opinion in Ultramares Corp. v. Touche, noted that allowing tort recovery for economic losses would effectively eliminate the line between tort and contract and expose a party “‘to a liability in an indeterminate amount for an indeterminate time to an indeterminate class.’"
In Indianapolis-Marion County Public Library, the owner advanced five arguments against the application of the Economic Loss Doctrine, including: 1) “other property” was damaged; 2) the damages were physical or created imminent risk of physical harm; 3) the defendants are professionals; 4) the defendants negligently misrepresented facts; and 5) the defendants provided solely services and not tangible products.
So what constitutes other property in the context of the Economic Loss Doctrine? In Indiana, the issue is addressed by examining what product or service was secured by the plaintiff. The rationale behind this approach is that a supplier of an allegedly defective product or service is only in a position to bargain for the appropriate risk allocation with the purchaser relative to performance expectations. However, a supplier of a component product or service cannot generally negotiate with the end user or consumer. If damage to the finished product constituted other property, suppliers would be subject to uncertain liability, which is an underlying policy justification for the application of the Economic Loss Doctrine. To provide further context, in Indianapolis-Marion County Public Library, the Court found that the Library purchased a complete, renovated library and parking garage. The alleged defective “products” were the designs, construction materials and construction services, all of which collectively comprised the final product. Accordingly, the Indiana Supreme Court held that any physical damage in the completed facility would not and could not constitute “other property”.
Having decided that the plaintiff’s damages were not to other property, there was no reason for the Indiana Court to address the argument that the Library’s damages were physical damages to property. Nevertheless, the Court addressed the owner’s contention that the alleged defects created an imminent risk of physical harm, thereby excepting this case from the economic loss rule. Here, the Court simply relied on the precedent it established in Progressive Ins. Co. v. General Motors, Corp., which precluded a strict tort products liability action where the absence of personal injury was concededly fortuitous. Consequently, the Court held that the Economic Loss Doctrine applied the owner’s negligence claim despite the alleged presence of imminent risk of physical danger.
Regardless of the nature of injury, the Library maintained that the Economic Loss Doctrine should not apply to professionals, negligent misrepresentation claims and/or defective services.
The owner contended that the Economic Loss Doctrine should not be applied to design professionals as a matter of law. The Library compared design professionals to other service professionals (e.g. attorneys) where tort liability exists based on duties that arise outside of contractual obligations. For support in extending such a paradigm to design professionals, the plaintiff relied on Peters v. Forster where the Indiana Supreme Court found that design professionals owe a duty of care to third parties where injury is foreseeable.
The Court rejected this analysis in relying on decisional law of other jurisdictions which addressed the application of the Economic Loss Doctrine to design professionals. The foreign decisions were divided into cases where privity of contract was present and cases where it was not.
Where plaintiffs were in privity of contract with the defendant-design professional, the Indiana Supreme Court cited Arizona and Nevada opinions in finding no justifiable distinction for applying the Economic Loss Doctrine to contractors while allowing tort claims against design professionals. There was simply no differing policy concern underlying contractors and design professionals relative to the application of the economic loss rule since each were being charged with alleged qualitative dissatisfaction in the performance of contractual duties.
In circumstances where plaintiffs are not in contractual privity with the defendant-design professionals, the Court ruled that the absence of a contractual right of action would not therefore create a negligence liability against such parties. Alternatively stated, the Library did not acquire an impermissible right of action against those entities who were not in privity of contract with the owner.
The Indiana Supreme Court clearly recognized that permitting tort recovery for qualitative injuries would undermine and frustrate the bargained-for allocation of risk throughout the network of agreements without any overriding “unfairness” to justify upsetting the negotiated balance. A project owner allegedly sustaining economic losses is permitted its rights of action against those entities in privity of contract (or against those who extend warranties in their favor). Those entities may, in turn, pursue their derivative contractual rights against their privity parties through the network of contracts until liability resides with the ultimately culpable and responsible party. As such, the Indiana Supreme Court held that the Economic Loss Doctrine precludes negligence actions by owners against design professionals wherever and whenever the underlying claims consist of nothing more than defeated or diminished contractual expectations.
The Library’s position respecting the negligent misrepresentation exception to the Economic Loss Doctrine was summarily rejected by the Court. Of interest, no distinction was drawn between those engagements where the design professional’s services results in a tangible improvement to property as opposed to those where “pure information” was provided (e.g. an architect’s building audit for a prospective purchaser). Here, the Court held that the negligent misrepresentation exception was inapplicable since the Library and defendants were connected through a series of contracts.
The arguments limiting the application of the Economic Loss Doctrine to qualitative dissatisfaction in tangible product disputes, as opposed to services, was also summarily rejected. Again referencing the policy considerations underlying the Economic Loss Doctrine, the Indiana Supreme Court failed to recognize a meaningful distinction in the application of the principle in product and service settings.
The Indianapolis-Marion County Public Library decision not only provides a long-needed and definitive Indiana statement on the application of the Economic Loss Doctrine to design professionals, it raises and explores the universal policy considerations associated with the rule’s implementation where contractual interests are at issue. Quite simply, a party seeking recovery for defeated or invalidated expectation interests should not be permitted the extension of tort law for dispute resolution which can only serve to eviscerate the contracting parties’ intentions and agreed to risk/reward allocations.

The United States District Court for the Northern District of Illinois recently held in
In a
The Second District Appellate Court of Illinois recently
In .jpg)
The Second District held as much in its recently released opinion in
You may recall
In the recent decision of 
In
It’s still in its infancy, but Google Scholar’s beta version allows you to search scholarly articles, patents or legal opinions and journals. Here’s a sample search for “
According to the
We’ve been lax lately in getting our readers interesting district court opinions on topics that are facing the industry. Today we’re pleased to rectify a small portion of that delinquency with
Post hoc ergo propter hoc
We’ve been writing with updates regarding the
Ezra Klein
Restrictive covenants
In limiting and answering a certified question regarding Section 5(b) statements under the
2009 has been an exciting year for Section 5 of the
Here’s a bit of trivia for today. The name of the clause at the foot of an affidavit or any other oath administered by an official that describes when where and in front of which official the oath was sworn is called the “jurat.” 
If people really bought into the adage that you can’t fight city hall, or at least the asserting-your-rights-against-a-state-seeking-to-infringe-on-them principle that it represents,
If there’s one thing our legal system abhors, it’s a lie. Apart from just making a decision about liability or guilt, juries help ferret out the veracity of our fellows by listening to live testimony and making a decision about credibility. The success of a lie, its perpetration on our populace,
In
It’s not that often that we get to see an in depth analysis of a factual scenario in a construction dispute case. It is even less often that such an analysis is performed by the 7th Circuit.
Yesterday
In using most standard-form agreements on a particular project the primary parties tend to negotiate the specific terms and reach an accord that will either include or exclude arbitration as their chosen form of primary dispute resolution. Opinions on the effectiveness and usefulness of arbitration are as varied as the fish in the sea.
federal circuit court found that a state court determination could preclude it from considering an issue regarding the arbitrability of a contract dispute.
“An ounce of prevention is worth a pound of cure.” Benjamin Franklin’s idiom is well suited to many aspects of life and the construction industry is no exception. In yet another case involving elements of design and construction that are in conflict with the Fair Housing Act, the
The court rejected the argument that the provision could be read to imply that attorneys’ fees would be awarded to R.R. Donnelley in a dispute with Vanguard over the enforcement of the indemnity provision. Instead the court found that the “by an entity” phrase could not be read to include Vanguard. The court found that the provision applied to disputes between R.R. Donnelley and others, but not between R.R. Donnelley and Vanguard for the enforcement of the indemnity agreement.
Reading the opinion, its apparent that the alleged reason for failing to close on the unit, with a purchase price of over $2 Million, was that an additional floor of parking was added after the initial earnest money deposit was tendered. The plaintiff’s argument was that the addition of parking made the price he had paid for his parking spot unfair given that the additional parking reduced the value of the spots. He also alleged that the additional floor of parking increased the maintenance fees for the association.
For those of you faced with any attempt by a plaintiff to claim that the implied warranty of habitability can be extended to a design professional, relief has been afforded.
The recent case of
It’s a long time to wait to get paid, but a new
The recent case of
It’s a case worth parsing through if you have the time because the Municipalities you deal with could be exacting costs from you that are not allowed under State law and that you could recoup.
Over the past two years we’ve seen quite a few Acts from the Illinois legislature regarding the industry and its operations. We’re still waiting on good case law interpreting the
It’s New Suit Friday and this week we have some new cases that just about every reader will be interested in. From attorneys looking at sample complaints and causes of action to design professionals, owners and contractors wondering what issues they might face and what could give rise to liability, this week’s spot is interesting.
Those of you follow our blog know that we've been waiting for the
as proof of your coverage as an additional insured. In
For those of you following the Illinois Supreme Court's decisions regarding mechanics liens, you will be happy to know, that the Court, will be releasing its Weather-Tite decision on
There haven’t been very many interesting cases for this week’s New Suit Fridays here are the few we’ve pulled for you:
We first wrote on the travails and
In what is sure to be a case you’ll want to follow… the 

The first district has upheld an arbitrator’s decision regarding the implication of an indemnity provision and given us a useful reminder that some rote contract language is actually important.
in his wife’s name was not a factor that would protect him – he ran the business and acted as though its assets were his own.
Without extrinsic factors altering the situation, generally only the people in possession and control of a property are liable for its negligent maintenance. Most often, the lessee who is in possession is liable for injuries sustained by third-parties and caused by a failure to keep the property in good repair.
The acts alleged in the complaint are important for home-owners and can act as a guideline or at least offer some insight about things to look for when contracting for repair and remodeling work:
In 
The fact that everyone communicates with e-mail these days should get you thinking about putting a document retention policy in place and having company policies for the use of all your electronic media. The Illinois State Courts are far behind the Federal Courts in addressing the issue of electronically stored information and how to handle it in discovery. However, it is not unlikely that you could find yourself in Federal Court or that the Illinois State Court’s could implement their own plans and procedures regarding this information.
failure to include a copy of the MWRDGC’s Affirmative Action Ordinance’s required “Utilization Plan” with the bid is a material failure which allowed the rejection of the applying joint-venture’s low bid and the award of the contract to the next-highest bidder.
In Newton, the
court opinion
As part of the construction project, Henderson erected/constructed a metal-grated platform as part of an air bridge that was to provide access to the center of a digester (large concrete tank used to treat wastewater). Two weeks after Henderson had installed the metal- grated platform, Plaintiff was walking on the platform when a portion of the metal grating collapsed causing him to fall into the digester. At the time of the accident, the metal grating was not secured with banding at the edges or with attachment clips at the ends as specified in the manufacturer’s installation instructions. The specification for the metal grating, included in the construction documents, required that the edges of the grating be secured with banding bars and that the metal grating be installed in accordance with the manufacturer’s installation instructions and approved shop drawings. The manufacturer’s instructions, which stated that the grating should be banded at the edges and secured with at least four attachment clips at each end, were contained in a shop drawing approved by Baxter & Woodman and included as a specification in the construction documents. 
The suit was brought to stop the proposed construction of a multi-unit condominium by an existing multi-unit condominium building next door to the construction site. As we said, the opinion states that the named plaintiff is the association for the existing condominium, but the board of directors brought the suit. The defendants challenged the standing of the board of directors to bring the suit because the board had not gotten the 2/3’s vote of the association’s members required by the condo’s by-laws for the board to bring suit on behalf of the association. The trial court dismissed the case and all the parties apparently agreed that the suit could be brought if the vote were taken and 2/3 majority voted to sue. The plaintiff appealed the issue. (other issues were also raised by defendants on appeal based on the trial court’s dismissal, but they are not the topic of the opinion nor the topic we are addressing).
Quite a lot of commotion has been tossed around regarding the opinion of the appellate court. Some people see it as declaration that the landmarks ordinance is unconstitutional, but the truth is that the appellate court seemingly went out of its way in the opinion to say that they were simply stating that the plaintiffs had put enough information in their complaint to state a claim against the city on the grounds that the ordinance is unconstitutional.
The relationship went south over disputes about payment and budgeting. The architect sent the vet a letter warning that all the plans they had produced were proprietary and that no one could use them to complete the project and demanded return of the plans. The vet responded that the plans were useless and that they had been “rolled up and discarded.”
those measures could create liability we didn’t have before and could erase protections we contracted for.
them on September 24, 2001, and although they had allegedly had conversations about the suit with their insurance broker, they waited until January 19, 2004 – over 27 months – to tender written notice of the suit to their insurer. The case had been ongoing for over two years and was set to go to trial in March of 2004.
In 2003 the theatre had the roof inspected because it had been leaking. Shortly after the inspection, the theatre sent the mall a letter requesting that the mall replace the roof. The mall did not respond and the theatre had its attorney send another letter that said:
In the circuit court, the designer’s lawyers argued that the contract provision at issue meant that the four-year statute of limitations period began to run in 1997 thanks to the AIA contract provision. The trial court agreed and dismissed the action. The owners appealed and argued that a different section of the statute of limitations provisions (
It’s not every day that we get to scoop the 

International
Neither of these arguments is very good. The second is laughable. While it is true that the Illinois Supreme court has yet to specifically address this issue, many courts have already reasoned that because the work is performed by a licensed architect, it is the licensure – which is proof that standards are met through the design professional’s credentialing process - that keeps the public safe, which is the point of the process. The fact that an entity may register as a professional design firm has nothing to do with public safety; public safety is the policy behind the act that requires registration. The court upheld the contracts and their arbitration provisions and allowed the action against the design professionals to proceed in arbitration against the desires of the plaintiffs.
stated the two were joint venturers for bidding, performing under the contracts and completing the project. If the bids were awarded, they were to be entered into in the names of the parties as joint venturers. They were to share losses and profits. Party A would provide all the labor and payroll and taxes and worker’s compensation and was entitled to reimbursement for those expenses from the JV before it and Party B split profits. IDOT awarded the JV the contract and in 2000 an accident occurred at the project where employees of Party A, employees of Party A and whose worker’s compensation premiums were paid by Party A were injured. The injured workers filed for and received their workers’ compensation benefits through Party A’s workers’ compensation insurer. This was their sole remedy against Party A under the 
As there was no evidence that plaintiff’s work was part of an overall plan to improve the property, its work was not a lienable activity under the Act.”
and indemnify the defendants to a lawsuit under a policy issued to a non-party for an accident at a construction site involving a scaffolding collapse in 2002. The entities seeking indemnification and defense owned the building and had entered into a construction contract with a non-party to the underlying suits in 2000 and the insurance coverage required by that agreement lasted into the time of the accident.
While the question didn’t seem to hinge on too many specifics in the actual contracts between the two parties, the court did take time to note that any legal distinction between the two was nullified by the terms of the contract at issue which allowed that the creditor could pursue the guarantor without first pursuing the principal. (This is important given that the classical difference between a surety and a guarantor involved the surety’s obligation as joint and several and the guarantor’s obligation as derivative and actionable only when the principal cannot pay). 
construction project. .jpg)
The plaintiff was a sub-contractor hired to perform services for the removal, hauling and disposal of rock and gravel from a site for the construction of a new school.
In situations where the fee is a fraction of the total project cost, consider the personal guarantee.
coverage under a standard CGL policy to a subcontractor.
2)
In 