International Production Specialists, Inc. v. Schwing America, Inc. - delay, contract, damages and the 7th Circuit
It’s not that often that we get to see an in depth analysis of a factual scenario in a construction dispute case. It is even less often that such an analysis is performed by the 7th Circuit.
In the recent case of International Production Specialists, Inc. v. Schwing America, Inc. (Doc. No. 07-3632) the facts were an integral part of the appellate court’s decision to uphold a district court’s determination regarding delay.
A full recitation of the unique situation can be found in the opinion linked above. In short, IPS sued Schwing after Schwing terminated a contract with IPS under which IPS was to supply several silos for a waste treatment facility. Schwing terminated alleging delay on IPS’ part. The contracts had been negotiated and even suspended for a period of time over the course of three years. However, once the contracts were negotiated for a final time and work resumed, Schwing was correct in assuming certain negotiated time-frames and rightfully terminated the contract when IPS failed to perform within time-frames that, while not specifically delineated in the final contract, were at least feasible under previous iterations of the parties’ agreements.
The court upheld the decision in favor of Schwing and also reduced a breach of contract damages award under a theory of betterment for money Schwing was awarded that it hadn’t actually lost through payment to IPS.
The decision is important for anyone looking to understand a nuanced delay scenario and will be of interest to parties looking to re-negotiate terms after suspension or through a mutual decision to alter material terms. What’s most important is the consideration of previous performance obligations under an altered construction contract to determined unspecified altered or corrected present obligations. Again, delay is often a basis for terminating a contract and the damages resulting from delay can be steep, but as we’ve said before, the point of the action against another for breach of contract is not putting a party in a better position than it would have been if there was no delay and no breach.
the essence” clauses in contracts.