Could Adding The Term "On Demand" to My Indemnification Provision Protect My Ability To Bring A Claim Within A Ten-Year Statute of Limitations?
The recent case of Peregrine Financial Group, Inc. v. TradeMaven, LLC, has at least offered some guidance.
In Peregrine, both the plaintiff and the defendant had been sued in another action over a patent dispute. The initial action had been resolved by a federal court through a settlement between the parties and the plaintiff in the patent action and a consent judgment had been entered.
The indemnity provision in the TradeMaven contract stated that it agreed to hold Peregrine harmless from any claims for “expenses and costs (including any reasonable legal fees and expenses related to [Peregrine’s] defense) arising from any claim of infringement of any trademark, service mark, trade name, copyright, or other proprietary right.” In the patent suit, the parties placed a provision in the consent judgment that each party would bear its own costs and attorneys fees.
After the federal suit, Peregrine sent a letter to TradeMaven’s counsel requesting the $416,081.22 in attorney's fees. TradeMaven didn’t indemnify Peregrine for the fees so Peregrine filed the indemnification claim in state court for recovery of those fees. The state district court ruled that the claim was precluded by res judicata.
One of Peregrine’s arguments on appeal was that even if Peregrine could have brought its claim for indemnity in the federal suit, it didn’t need to because a previous Illinois Supreme Court Case, Guzman, held that the claim for indemnification did not accrue until after the patent dispute concluded and TradeMaven rejected Peregrine’s written demand for indemnification.
Guzman ruled that the 13-204 statute of limitations was applicable in construction defect contract dispute for indemnification between a defendant and a third-party in a situation where the third-party suit had been brought with three counts – implied indemnity, express indemnity, and breach of contract – and the opinion was rendered without an express statement of which theory the Court was considering.
The Appellate Court in Peregrine rejected Peregrine's argument and said that Guzman involved an “implied contract of indemnity” and a third-party complaint and that the instant case involved no third-party action where both parties had been named as defendants in the federal action and that the parties had an express contract of indemnity.
Peregrine then argued that the more recent Illinois Supreme Court decision in Travelers extended Guzman to express indemnity agreements. The Appellate Court said that because the indemnity provision in Travelers contained the words “on demand” – “Payments of amounts due Surety hereunder together with legal interest shall be payable on demand” – the express terms of the indemnity agreement in Travelers implied that the indemnity action did not accrue until demand was made and therefore, the instant action was different because the indemnity provision at issue in Peregrine contained no language providing that payment was triggered by demand for payment.
In Travelers the Supreme Court apparently determined that the fact that the Guzman did not especially state whether it was addressing the nature of the indemnity claim on a breach of contract, implied indemnity or express indemnity basis meant that Guzman did not provide enough guidance to aid in the assessment of a suit based on express contractual indemnity.
Travelers also held that implied contractual indemnity is only available in tort. Which makes it odd that the court in Peregrine could say that the claim in Guzman was about implied contractual indemnity because it was a construction defect case and not one about a tort.
Travelers also didn’t offer guidance on whether carefully constructed indemnity provisions in regular construction contracts could serve as the basis for a claim for breach of contract premised upon the breach of an indemnity provision thereby making them claims regulated by the ten-year statute of limitations addressed in Travelers, or whether a claim for "express contractual indemnity" was different than a breach of contract claim and in construction defect case which could be brought as a third-party action (the commercial equivalent of contribution). In the second type of claim, the defendant is basically saying “if I’m liable to the plaintiff, it is because this third party made a mistake.” In the latter instance, Travelers would seem to imply that the four-year 13-214 statute of limitation would apply because the claim was based on the construction defect, in the former, because the claim is actually for failure to indemnify after a demand, it would appear that this is a 13-206 matter as discussed in Travelers.
By distinguishing the Travelers case based on the demand language the Appellate Court in Peregrine has created an interesting distinction and not resolved the issue created in Travelers regarding how and under what theory a defendant should sue a third-party in a construction dispute not based on negligence such as one where the party is looking to pass-through any potential economic damages. Another question raised by these line of cases:
- Is the claim properly one for "express contractual indemnity" because there is an indemnity provision of the contract and the third-party contract was breached, or is it a claim for breach of contract for breach of the indemnity provision or both?
We know that professionals and contractors should arguably include indemnification for “economic damages” in their indemnification provisions if they want to attempt to recover those forms of damages at a later date. Friedman, Alschuler & Sincere v. Arlington Structural Steel Co., Inc., 140 Ill.App.3d 556, 489 N.E.2d 308 (1 Dist., 1985). Friedman and a line of cases following it support the contention that the indemnity provision needs to be specific as to the type of damages the parties will be able to seek, but nothing has settled the question raised by Travelers about where and when, if the provision is drafted properly, a party, if at all, must seek this contractual indemnity and what the cause of action actually is in third-party claims for construction defect where someone is looking to pass-through the claims of another.
For now the best practice seems to be to ensure that the contractual indemnity provisions include the “on demand” language in an effort to preserve a claim and to assert both a claim for express contractual indemnity and a claim for breach of that provision as a breach of contract.