The Validity of Municipal "Impact Fees" For Contractor/Developers

It’s a case worth parsing through if you have the time because the Municipalities you deal with could be exacting costs from you that are not allowed under State law and that you could recoup.

In Raintree Homes, Inc. and Raintree Builders, Inc. v. The Village of Long Grove (2nd Dist. Doc. No. 2-06-1105) the second district appellate court was faced with the review of a district court’s determination that the provisions of the Village of Long Grove’s “impact fees” that were assessed on those applying for building permits were void under the Illinois Municipal Code (65 ILCS 5/1-1-1 et seq.)

The Village had been assessing “impact fees” which had increased in cost over the years from 1993 to 1997 against anyone applying for a building permit pursuant a village ordinance (Section 4—1—4 of the Long Grove Municipal Code which was repealed in 2003 and new “fees” have since been implemented). A statement contained in the “impact fee” provision of the code contained a description regarding the purpose of the fee as being for parks and schools, but the application of the money showed that some went to the Village, some went to the schools and parks for different purposes, and the district court found that none of the uses comported with what was allowed under the Illinois Municipal Code.

The appellate court upheld the ruling and the court’s order that the Village pay back to Raintree some $114,700 in impact fees that it had paid from 1993 to 1997.

The appellate court’s decision found that because the funds from the impact fees were put into a general operation fund rather than being used for the purpose of improving/funding or having to do with “school grounds” which is a term elaborated upon by a 2002 opinion (Thompson v. Village of Newark) and augmented by a 2003 amendment to the code to include “land or site improvements, which include school buildings or other infrastructure.”

The appellate court also held that the portion of the fee attributed to the parks and other various land improvements or “open space” was not tailored pursuant to the Illinois Municipal Code to limit the use of the fee to “only newly acquired open space.”

The opinion also contains a lengthy analysis and discussion of “duress” concerning a business’ need to pay for a fee given the need to have the license or benefit conferred by paying the fee for the operation of the business and its later ability to contest the fee without losing that right under the voluntary payment doctrine.

The important part here is that Raintree got the fees back. This was in large part due to the specific manner in which the purpose portion of the municipal code was drafted and the distinct method in which the funds were distributed and used. It is likely that a statute that was more vague and less accurate testimony regarding the application of the fees would have offered a different result even if the fees were applied the same.

For contractors and developers forced to pay such fees, the lesson is to find out what they’re for and how they’re being used. The lesson for municipalities is the craft the statutes correctly to make sure the money is being used properly.

Thumbprints Are Coming

The Sun-Times has a short piece today on SB 0456 which became Public Act 95-0998. We first reported on this bill back in May of 2008. The Sun-Times’ article reflects that the bill will go into effect on June 1. If you scroll down to Sec. 3-102(h), you’ll see that the failure of the notary to get the fingerprint as part of the record doesn’t mean much outside an allegation of fraud:

(h) The failure of a notary to comply with the procedure set forth in this Section shall not affect the validity of the Residential Real Property transaction in connection to which the Document of Conveyance is executed, in the absence of fraud.

Also, if you’re a property owner with some reason to worry about providing your thumbprint, the act has a provision regarding how and when these records will be disclosed:

(i) The Notarial Record or other medium containing the thumbprint or fingerprint required by subsection (c)(6) shall be made available or disclosed only upon receipt of a subpoena duly authorized by a court of competent jurisdiction. Such Notarial Record or other medium shall not be subject to disclosure under the Freedom of Information Act and shall not be made available to any other party, other than a party in succession of interest to the party maintaining the Notarial Record or other medium pursuant to subsection (d) or (e).

The weirdest part about the whole act is that most of the changes will be nullified by the statute’s own language on July 1, 2013 unless the legislature acts by then to amend the law:

(k) Subsections (a) through (i) shall not apply on and after July 1, 2013.

Shovel-Ready Illinois

Stimuluswatch.org is reporting on the stimulus package and the projects proposed for Illinois. A link to the Illinois projects is here. The database is searchable and includes the localities, descriptions of the projects and the amounts proposed.

 

 

Mechanics Liens Are Another Tool for Repayment... When They're Done Right

            Any business engaged in the construction industry in Illinois should be aware of the rules and requirements for filing a mechanics lien, or at least have someone they can reach out to in order to answer those questions.

            The statute is possibly the best method available to any contractor, architect, sub any other person working on a project for ensuring payment.  It creates an encumbrance on the land that allows not only for foreclosure, but also forces subsequent buyers to deal with the encumbrance before moving forward by either bonding around the lien or attempting to extinguish it.  Whether the claim is for $1,000 in work or for $10,000,000, no matter what the amount, if the requirements are met, you can avail yourself of the act and pursue payment.  Depending on the exact situation, the act may force you to get something filed and deliver notice anywhere from 90 days to four months after your last date of work, and knowing and complying with the act’s guidelines helps ensure another method for getting paid (the act also allows for attorney’s fees).  If you don’t you will lose your rights and while the amounts of each account receivable may not seem like a lot, if everyone starts to skimp on the receivables, the effect of non-payment can become calamitous to your business.  In the current economic climate, even if you know that payment is down the road, it’s best not to sit on these rights and lose them… talk to someone and get it done right.  Because if its not done right, you could end up like the plaintiff in Speedy Gonzalez Landscaping, Inc. v. O.C.A. Construction, Inc., (1st Dist., Doc. No. 1-07-2370).

The plaintiff was a sub-contractor hired to perform services for the removal, hauling and disposal of rock and gravel from a site for the construction of a new school.  The plaintiff performed its work and sought payment for some $637,382.53 that it was owed.  Because the project was for a public building improvement built with public funds, section 23 of the Illinois Mechanics Lien Act applied.  The plaintiff complied with the applicable notice required by the section for delivering notice of its lien to the Public Building Commission of Chicago.  The plaintiff then properly filed its complaint against the defendants asking for an accounting within the applicable 90-day time limit from the filing of the notice, but failed to abide by the statute and also deliver a copy of the complaint to the public body within the time limits.  The GC filed a motion to dismiss the claim based on the failure of the plaintiff to follow the applicable time requirements and the court granted the motion, thereby barring the plaintiff from its count for a mechanics lien.  The appellate court upheld the decision of the trial court. 

For the simple failure to provide a copy of the complaint to the right person, the plaintiff has lost its mechanics lien claim.

 

Counting on TIF Funding... Not So Fast

Malec v. City of Belleville (5th Dist., Doc. No. 05-07-0456) is a case worth noting.  The City of Belleville adopted a group of ordinances in 2006 that provided for the formation of a tax-increment-financing district (TIF) pursuant to the TIF Act.  The city also adopted an ordinance creating a business district, approved a redevelopment plan, tax increment allocation financing for the Developers, a tax within the created business district and authorized the use of general sales tax revenues to reimburse the Developers for project development costs.  A complaint filed by the plaintiff alleges that these ordinances were to help finance a Wal-Mart, Lowe's, housing development and some other businesses.

Plaintiff, a taxpayer, brought suit challenging the city's enactment of the taxes under the TIF Act.  The district court dismissed the plaintiff's claim, finding that he lacked standing to bring his action as a taxpayer.  The 5th District reversed and found that if the actions of the city in creating the TIF and business district did affect the general revenue of the city, then a taxpayer would have standing.  The court also held that the taxpayer could challenge the creation of the TIF through claiming that the areas that had been created did not meet the criteria of being "blighted" as the Act required (under the act "blighted" is a term of art that requires a area meet a myriad of factors in order to qualify for the TIF districting).  See 74.4-3(a) of the Act.  The argument was that the areas would have developed as business districts on their own, and as such, the creation of the special districts to generate revenue that would be paid to the developers affected the general revenue of the city because the city would have generated the revenue for itself and would therefore have no need to pay developers to do it.  (No mention of the timing was made, i.e., whether an argument that a development district would create business in a matter of a year as opposed to a naturally occurring district developing over, say, ten years).

While the case is not a blow to the creation of the districts for development, it does lend individuals another form of suit which could be used to slow down any form of development relying on TIF funding and is a case we'll keep an eye on.

The Chicago Province of the Society of Jesus v. Clark and Dickens, LLC (1st Dist. Doc. No. 1-07-0960)

falling in.JPG

This is a case from the first district about the collapse of a building in Chicago.  The Chicago Province of the Society of Jesus (a Jesuit organization) had a building and demolition work adjacent to the building went awry causing the collapse of the Jesuit's structure.

The parties (and there are many) sued each other and some of the defendants decided to settle.  In total, the Jesuits sought close to $3 Million in damages from the defendants on theories of negligence, violation of the Adjacent Landowner's Excavation Protection Act and violation of the Illinois Municipal Code.  Six of the defendants offered a total of $1,185,000 to settle the claims made against them.

In Illinois, parties can seek a "good faith finding of settlement" under the Illinois Joint Tortfeasor Contribution Act allowing a party that settled to be discharged not only in settlement with the plaintiff, but also from all liability to any other party that might be pointing a finger in their direction.

Here, some of the parties that did not settle objected to the attempts by the settling defendants to obtain a good faith finding because that finding would mean that the non-settling defendants could not seek any more contribution from the settling defendants and would be left paying for whatever damages might be assessed down the road.

In addressing the matter, the court provided a decent summary of the relevant case law and standards regarding "good faith" findings of settlement and upheld the trial court's determination that the settlements were made in good faith.  Effectively allowing the settling defendants to have their liability capped and be removed from the case.

Korte & Luitjohan Contractors, Inc. v. Thiems Construction and IDOT (5th Dist, Doc. No. 5-05-0516)

In this case, subcontractor brought a suit against the Illinois Department of Transportation (IDOT), and the general contractor on a project.  The bid on the project was to perform services for the general to excavate a trench, install a sewer pipe, and supply backfill.  The contract required that the parties abide by the IDOT Standard Specifications and the plans specified in the general contract.  The suit alleged a claim for foreclosure under the mechanics lien act, in which IDOT was named a party, a claim for breach of contract, and a claim that the GC had violated the State Prompt Payment Act (30 ILCS 540/0.01 et seq.)  The trial court dismissed IDOT from the case, and found that the IDOT specs precluded the breach of contract and lien actions.  The trial court then determined that retaining payment was improper and awarded interest under the State Prompt Payment Act.  The parties appealed.

Here, the appellate court concluded that the trial court was right in dismissing IDOT given that the mechanics lien act authorizes the funds to be set aside before resolution of the issue, but does not authorize making a state agency party to a foreclosure action. The opinion discusses a topic that should be of interest to those contracting with the state when it considers payment under the mechanics lien act.  §23 of the act authorizes subcontractor remedies through liens against public funds for state projects, but the act has never applied to contractors.  Additionally, suing pursuant to this section means that a subcontractor will be bringing an action for an accounting within 90 days of providing the required notice, and the only way to bring in an officer of the state under the act is in an action claiming they failed to comply with §23 of the statute.

The breach of contract claim filed against the GC was premised on an interpretation of IDOT Standard Specifications.  (This may bore some of our readers, but it is actually pertinent to anyone looking for courts to favorably interpret government specs.)  §208.03(b) governs methods of measurement quantities for trench backfill, and contains a clause stating that any backfill required in excess of the maximum quantity as calculated but he specs "shall be furnished by the Contractor at his/her own expense."  The plaintiff argued that there was no established width to the trench and tried to say that use of the word "shall" in §550.04 (the IDOT spec which states exactly how wide a trench should be on such a project) didn't really mean shall, but meant something like "shall not be less than," which, you don't have to be Bryan A. Garner to understand, is bad form in just about every school of legal interpretation... especially when the court can read other sections of the IDOT specs and see that when IDOT meant to set a minimum limit on something, it used some variant of "shall not be less than" and not just "shall."

Utilizing this reading of §208.03 the court upheld the trial courts determination that the plaintiff was not owed monies for the excess it was required to provide and the dismissal of the breach of contract claim was proper.

With regard to the final argument, the court held that it was IDOT that failed to make prompt payments to the GC who, pursuant to provisions of the contract and federal regulations was then to turn around and hand the money over to the plaintiff.  Contrary to the trial court's opinion, the GC was not in error when it did not turn over monies that had not been forwarded by IDOT.  The GC would only be in error if IDOT had turned over the funds and then the GC failed to pay them to the subcontractor.  The appellate court also said that the trial court had properly interpreted the State Prompt Payment Act, but because the GC did not owe money to the plaintiff, there was no violation of the act.

[NOTE: In addition to the State Prompt Payment Act, there are other prompt payment acts that can be alternative sources for causes of action regarding getting paid such as the Contractor Prompt Payment Act, the Local Government Prompt Payment Act, any of which, along with a host of other methods, can be utilized under the law in securing payments owed.]

Statutes of Repose and a Duty to Maintain

We've previously discussed the Illinois construction statute of repose (735 ILCS 5/13-214).  The benefits it conferred to design professionals and others by the statute's ten-year limitation cannot be underestimated. 

In Ryan v. Commonwealth Edison Company (Doc. No. 1-06-3309, 1st Dist. Ill. App.) the Illinois first district appellate court has broken with itself and sided with the third district in asserting a "status/activity" distinction for claims that will be barred under the statute of repose.

The court was confronted with the issue of whether Com Ed's duty to maintain a transformer that exploded and injured the plaintiff was separate and apart from its installation work and therefore, not subject to the statute of repose.  The court found that Com Ed's status as an installer and any claims that arose from the installation might fall under the statute of repose, but made a determination that since Com Ed had a duty to maintain the equipment (derived from its capacity as the power supplier and not its status as the installer) the statute would not apply.

  • Now that we have a definite split, we could see the Illinois Supreme Court address the "status/activity" distinction.  More importantly, because the court made the determination regarding Com Ed's duty in this case, we should be alert for more judicial determinations of ongoing duty.  Will the decision only apply to utility companies supplying services which necessitate a duty to maintain equipment?  Even apart from any undertaking to maintain structures/equipment after installation?  Even when the duty has been contracted or left in the hands of some other entity like a municipality?

Denying a Municipality's Immunity and Interpreting the Statute of Repose

In Trtanj v. The City of Granit City (Ill. App. Ct., 5th District, No. 5-07-0002), the plaintiffs owned a house that was filled with sewage after a thunderstorm.  During the thunderstorm, three sewage lift stations that normally operated to transport sewage through the city's system were left without power.  The city took two to three hours in getting the sewage systems back online.  As a result of the rainfall and issues with a clay pipe connecting the plaintiffs' property to the city's system, water and sewage backed up into the plaintiff's home.  Prior to the motion for summary judgment brought by the city, the city's superintendent of water testified that it should only take 15 minutes to set up a temporary lift system and 15 minutes to get it operational.

The plaintiffs brought an action in 2002 and later amended their complaint in 2005 alleging negligence in the design, construction, operation and maintenance of the sewer system, that the backup was a temporary nuisance, and also brought an action in trespass against the city.  The city responded in a motion for summary judgment that the claims were barred under the statue of repose (735 ILCS 5/13-214), that the tort immunity act applied (745 ILCS 10/2-201) to protect the city from suit, and that it was not liable because the backup occurred during an extraordinary rainstorm.

The trial court granted the motion for summary judgment and the plaintiffs appealed.

The appellate court found that material issues of fact existed where the city had known about the outside water infiltration into the sewer system through the plaintiff's clay pipe; and where the city's own superintendent of streets had testified that it should only take 15 minutes to set up the temporary pumps, not the two to three hours that it did take.

In adjudicating the repose claim, the court said that the statute of repose applied only to the construction and improvements of real property.  Because the plaintiff had alleged that the design installation and construction of the sewer station was at fault, the court found that these allegations were barred by the statute of repose when the design, construction and installation had occurred more than ten years prior to the filing of the lawsuit. 

The court went on to find that the statute did not protect the city from the claims that the maintenance and operation of the sewer system and the lift stations that occurred after their installation and within the ten year period were negligent.

The court cited a previous case, Prochnow v. Elpaso Golf Clib, Inc., 253 Ill. App. 3d 387, finding that while those claims that involved the design, construction, supervision, observation or management of the construction were exempt if the acts were outside of the ten year period, the persons responsible for possession or control and suppliers of the materials used in the maintenance and operation were subject to liability for reason of construction defects.

The court then went on to address the city's claim of immunity.  Holding that the statute protects only those acts of a municipality that are shown to be both an exercise of discretion and a policy determination, the court stated that acts which are ministerial are not protected.  After a discussion of the differences between policy determinations, acts of discretion, and ministerial acts, the court found that because the city's operation of the sewage system was subject to statutory and regulatory guidelines the actions were ministerial, and that there were material issues of fact concerning whether or not the city complied with those guidelines.  "Once a municipality decides to perform pubic work, the municipality must perform the public work with reasonable care and in a nonnegligent manner" (Slip Op. at 13).

The court also found that the determination of what might amount to an extraordinary sum of rainfall was not before the court and presented a question of fact for the jury.

The appellate court reversed the trial court's grant of summary judgment to the extent it was inconsistent with the appellate opinion.

Of note to design professionals and construction companies is the application of the ten year statute of repose.  Getting done with the work and getting out will start the clock running on the ten year period.  However, if follow up maintainance work is performed, that work is still potentially the subject of litigation. More importantly for many claimants is the willingness of the court to interpret the immunity statute and discern between policy, discretion, and ministerial acts.  It should not be overlooked that too often courts are willing to apply the immunity statute without adherence to the guidelines or undertaking the analysis to determine the exact nature of the act, perhaps inspections, construction, and maintenance can all be pled correctly to make certain the municipality has to explain its actions rather than simply pleading immunity.