Legal Fees In a Construction Dispute?... You're Not Alone.

John Parnass over at Washington Construction Law, an excellent Washington State Construction Law resource, is reporting on this article from the Law Blog of the Wall Street Journal.  The Donald is suing his attorneys over the fees they billed in representing him in a construction matter.

Great quotes from Trump regarding the underlying dispute and legal case over the breach of the earth-moving contract in the construction of a Golf Course:

"I have a Ph.D. in legal fees. I know when fees are fair and when they are not."

"Ninety percent of the conversations I had ... were about legal fees, not the case,"

"We won the case because I'm a great witness."

Whether or not they've got their own TV Show, clients should work with attorneys to establish a beneficial fee structure and ensure that they're getting value for their money.

Statutes of Repose and a Duty to Maintain

We've previously discussed the Illinois construction statute of repose (735 ILCS 5/13-214).  The benefits it conferred to design professionals and others by the statute's ten-year limitation cannot be underestimated. 

In Ryan v. Commonwealth Edison Company (Doc. No. 1-06-3309, 1st Dist. Ill. App.) the Illinois first district appellate court has broken with itself and sided with the third district in asserting a "status/activity" distinction for claims that will be barred under the statute of repose.

The court was confronted with the issue of whether Com Ed's duty to maintain a transformer that exploded and injured the plaintiff was separate and apart from its installation work and therefore, not subject to the statute of repose.  The court found that Com Ed's status as an installer and any claims that arose from the installation might fall under the statute of repose, but made a determination that since Com Ed had a duty to maintain the equipment (derived from its capacity as the power supplier and not its status as the installer) the statute would not apply.

  • Now that we have a definite split, we could see the Illinois Supreme Court address the "status/activity" distinction.  More importantly, because the court made the determination regarding Com Ed's duty in this case, we should be alert for more judicial determinations of ongoing duty.  Will the decision only apply to utility companies supplying services which necessitate a duty to maintain equipment?  Even apart from any undertaking to maintain structures/equipment after installation?  Even when the duty has been contracted or left in the hands of some other entity like a municipality?

Denying a Municipality's Immunity and Interpreting the Statute of Repose

In Trtanj v. The City of Granit City (Ill. App. Ct., 5th District, No. 5-07-0002), the plaintiffs owned a house that was filled with sewage after a thunderstorm.  During the thunderstorm, three sewage lift stations that normally operated to transport sewage through the city's system were left without power.  The city took two to three hours in getting the sewage systems back online.  As a result of the rainfall and issues with a clay pipe connecting the plaintiffs' property to the city's system, water and sewage backed up into the plaintiff's home.  Prior to the motion for summary judgment brought by the city, the city's superintendent of water testified that it should only take 15 minutes to set up a temporary lift system and 15 minutes to get it operational.

The plaintiffs brought an action in 2002 and later amended their complaint in 2005 alleging negligence in the design, construction, operation and maintenance of the sewer system, that the backup was a temporary nuisance, and also brought an action in trespass against the city.  The city responded in a motion for summary judgment that the claims were barred under the statue of repose (735 ILCS 5/13-214), that the tort immunity act applied (745 ILCS 10/2-201) to protect the city from suit, and that it was not liable because the backup occurred during an extraordinary rainstorm.

The trial court granted the motion for summary judgment and the plaintiffs appealed.

The appellate court found that material issues of fact existed where the city had known about the outside water infiltration into the sewer system through the plaintiff's clay pipe; and where the city's own superintendent of streets had testified that it should only take 15 minutes to set up the temporary pumps, not the two to three hours that it did take.

In adjudicating the repose claim, the court said that the statute of repose applied only to the construction and improvements of real property.  Because the plaintiff had alleged that the design installation and construction of the sewer station was at fault, the court found that these allegations were barred by the statute of repose when the design, construction and installation had occurred more than ten years prior to the filing of the lawsuit. 

The court went on to find that the statute did not protect the city from the claims that the maintenance and operation of the sewer system and the lift stations that occurred after their installation and within the ten year period were negligent.

The court cited a previous case, Prochnow v. Elpaso Golf Clib, Inc., 253 Ill. App. 3d 387, finding that while those claims that involved the design, construction, supervision, observation or management of the construction were exempt if the acts were outside of the ten year period, the persons responsible for possession or control and suppliers of the materials used in the maintenance and operation were subject to liability for reason of construction defects.

The court then went on to address the city's claim of immunity.  Holding that the statute protects only those acts of a municipality that are shown to be both an exercise of discretion and a policy determination, the court stated that acts which are ministerial are not protected.  After a discussion of the differences between policy determinations, acts of discretion, and ministerial acts, the court found that because the city's operation of the sewage system was subject to statutory and regulatory guidelines the actions were ministerial, and that there were material issues of fact concerning whether or not the city complied with those guidelines.  "Once a municipality decides to perform pubic work, the municipality must perform the public work with reasonable care and in a nonnegligent manner" (Slip Op. at 13).

The court also found that the determination of what might amount to an extraordinary sum of rainfall was not before the court and presented a question of fact for the jury.

The appellate court reversed the trial court's grant of summary judgment to the extent it was inconsistent with the appellate opinion.

Of note to design professionals and construction companies is the application of the ten year statute of repose.  Getting done with the work and getting out will start the clock running on the ten year period.  However, if follow up maintainance work is performed, that work is still potentially the subject of litigation. More importantly for many claimants is the willingness of the court to interpret the immunity statute and discern between policy, discretion, and ministerial acts.  It should not be overlooked that too often courts are willing to apply the immunity statute without adherence to the guidelines or undertaking the analysis to determine the exact nature of the act, perhaps inspections, construction, and maintenance can all be pled correctly to make certain the municipality has to explain its actions rather than simply pleading immunity.

Make Sure There's Relief to Be Had

Here's a reminder from the Northern District of Illinois Bankruptcy Court.  In Vancil v. Tres Amigos (docket #06-71254) the owner of a property, Tres Amigos, was looking to extinguish liens filed by two subcontractors of Vancil.  Tres Amigos brought the action to extinguish the liens where the two subs had not properly served Tres Amigos with their 90 day notices under the Illinois Mechanic's Lien Act.

A problem arose when the Court noted the Tres Amigos had never made one of the subs a party to the action and that it failed to assert a claim against the other sub, which was a co-defendant.  The Court pointed out the Tres Amigos would likely have prevailed on its claim, had it not failed to properly plead actions for which relief could be granted against the subcontractors.

  • The lesson learned here:  Make sure all your ducks are in a row before time, effort and money are spent asking the Court for relief that cannot be granted.

Limiting the Time For Indemnification

    Here's a Seventh Circuit decision (Foskett v. Great Wolf Resorts, et al.) full of information regarding claim accrual for negligent design, indemnification, and the theory of risk allocation.  Two parties had entered into an asset purchase agreement with mutual indemnification clauses.  Buyer and Seller had agreed to a sunset provision in Seller's indemnification provision.  A claim accrued after the sunset provision and, on appeal, the court enforced the provision.

Professional Design Firms and Licensed Architects

There's certainly a difference between "registration" and "licensure"...
architect license copy.jpg

We've come across quite a few architects and engineers who seem to forget that a professional design firm needs to be registered.  It's an extra step, in addition to the professional's individual licensure and registration that's required in Illinois.  But what exactly is the impact of forgetting to register?

Here's an interesting case from the Central District of Illinois, pointing out that a contract will not be voided, and a developer's claim for restitution will not stand even if a professional forgets to register the design firm.  In Brethren v. OSM (C.D. Ill. 06-3161) the court points out that even though a firm may forget to register, the work was still done by a licensed professional and as such, there is no claim. 

Now, if the professional performing the work was unlicensed, certainly the restitution claim would be able to go forward.  The only real teeth the registration law has to compel the registration of the firm comes from the statute authorizing penalties for such a failure to register, 225 ILCS 305/21.  Work by a licensed architect is still work by a licensed architect.


IS THERE A NEW RELATIONSHIP IN THE CONSENSUSDOCS?

The new ConsensusDOCS forms were published late last year and will be the subject of the ABA Construction Industry Forum's 2008 Fall Meeting.  With all the buzz we thought it would be pertinent to sit down and read these documents.  This posting is one of many expected to come regarding the new ConsensusDOCS.

            The language implying a fiduciary duty hasn't changed much over the years and is often described by the courts as a "relationship of trust and confidence" between parties.  With that definition entrenched in case law we thought it a bit peculiar that the normal contracting relationship between an architect and an owner would be particularly described as one of "trust and confidence" in ConsensusDOCS 240 section 2.2. 

In the construction setting, plaintiff's with claims have been seeking to impose a fiduciary relationship in one form or another on contractors and architects to gain more damages and a heightened standard of care for some time.  Thankfully, many courts have often struck down the concept of parties contracting for construction services as entering into a fiduciary relationship thus allowing plaintiff's to bring causes of action outside the normal breach of contract claim or based on a heightened standard of care.  (See, 262 F. Supp. 2d 1004; 812 F. Supp. 72)

With the concept of "trust and confidence" and its implication of a fiduciary relationship in mind, it's odd that the ConsensusDOCS Guidebook from October 31, 2007, would explicitly delineate that the contracting parties should not be agreeing to a heightened standard of care:

  • "Standard of Care (Section 2.1): A definition of the standard of care applicable to architectural and engineering services performed under this Agreement is not included in this Agreement (previous additions of AGC contracts did include such a definition). The drafters of the new Consensus documents determined that it would be better for the design professionals to be held to a standard imposed on them by their own profession, rather than one defined by this Agreement.
  • "Contractors and Owners should not modify this Agreement by adding language that would hold any design professional to a standard of care that is above that which is customary and normal for design professionals in the same time and location, because that might result in the unintended consequence of voiding errors and omissions coverage available to the respective design professionals."

 
But then go on to say that the A/E is accepting a relationship of trust and confidence in Section 2.1 of document 240:

 

  • "Relationship of the Parties (Section 2.2): This provision requires the Architect/Engineer (A/E) to accept the relationship of trust and confidence in exercising its skill and judgment in furthering the interests of the Owner and expressly affirms the A/E's representation that it possesses the requisite skill, expertise, and licensing to perform the required services. The new language is preferable, but it should be noted that it was not included in the previous AGC 240 Owner-Designer professional Agreement, no longer published."

       It is also a bit boggling that understanding the implication of the "trust and confidence" language, that no other provision in the document would specifically state that nothing in the contract should be construed as creating a fiduciary relationship between the parties.  Perhaps the authors just thought such a provision unnecessary given the lack of case law supporting a fiduciary relationship in such a setting.  But why then be specific as to the language of "trust and confidence" between the parties?  Why not just state that the parties agree to "good faith and fair dealing" or accept a "contractual relationship for the provision of A/E services"?  And, even if a standard of care is not affected by the language, could "trust and confidence" through its fiduciary implications mean that there are now added duties that the A/E must be aware of?