The Statute of Repose and Mine Subsidence


In Ambrosia Land Investments, LLC, v. Peabody Coal Company (7th Circ., Doc. No. 07-1945) the Seventh Circuit tackled the fascinating question of whether or not the Illinois Construction Statute of Repose applied to a coal mine.  While we may not think this would be interesting to everyone, the construction statute of repose is actually a fun topic, and the 7th Circuit did a great job of covering the topic.

Along with a poignant discussion of the relevant Illinois case law regarding the statute, the court held that a coal mine on a piece of property would constitute an "improvement to real property for statute of repose purposes."  The court went on to find that the former mine owner was being sued as an owner of the mine and not as a party engaging in construction-related activities, so the plaintiff's case for damages to its property from mine subsidence did not fall under the activities covered by the statute.


Statutes of Repose and a Duty to Maintain

We've previously discussed the Illinois construction statute of repose (735 ILCS 5/13-214).  The benefits it conferred to design professionals and others by the statute's ten-year limitation cannot be underestimated. 

In Ryan v. Commonwealth Edison Company (Doc. No. 1-06-3309, 1st Dist. Ill. App.) the Illinois first district appellate court has broken with itself and sided with the third district in asserting a "status/activity" distinction for claims that will be barred under the statute of repose.

The court was confronted with the issue of whether Com Ed's duty to maintain a transformer that exploded and injured the plaintiff was separate and apart from its installation work and therefore, not subject to the statute of repose.  The court found that Com Ed's status as an installer and any claims that arose from the installation might fall under the statute of repose, but made a determination that since Com Ed had a duty to maintain the equipment (derived from its capacity as the power supplier and not its status as the installer) the statute would not apply.

  • Now that we have a definite split, we could see the Illinois Supreme Court address the "status/activity" distinction.  More importantly, because the court made the determination regarding Com Ed's duty in this case, we should be alert for more judicial determinations of ongoing duty.  Will the decision only apply to utility companies supplying services which necessitate a duty to maintain equipment?  Even apart from any undertaking to maintain structures/equipment after installation?  Even when the duty has been contracted or left in the hands of some other entity like a municipality?

Denying a Municipality's Immunity and Interpreting the Statute of Repose

In Trtanj v. The City of Granit City (Ill. App. Ct., 5th District, No. 5-07-0002), the plaintiffs owned a house that was filled with sewage after a thunderstorm.  During the thunderstorm, three sewage lift stations that normally operated to transport sewage through the city's system were left without power.  The city took two to three hours in getting the sewage systems back online.  As a result of the rainfall and issues with a clay pipe connecting the plaintiffs' property to the city's system, water and sewage backed up into the plaintiff's home.  Prior to the motion for summary judgment brought by the city, the city's superintendent of water testified that it should only take 15 minutes to set up a temporary lift system and 15 minutes to get it operational.

The plaintiffs brought an action in 2002 and later amended their complaint in 2005 alleging negligence in the design, construction, operation and maintenance of the sewer system, that the backup was a temporary nuisance, and also brought an action in trespass against the city.  The city responded in a motion for summary judgment that the claims were barred under the statue of repose (735 ILCS 5/13-214), that the tort immunity act applied (745 ILCS 10/2-201) to protect the city from suit, and that it was not liable because the backup occurred during an extraordinary rainstorm.

The trial court granted the motion for summary judgment and the plaintiffs appealed.

The appellate court found that material issues of fact existed where the city had known about the outside water infiltration into the sewer system through the plaintiff's clay pipe; and where the city's own superintendent of streets had testified that it should only take 15 minutes to set up the temporary pumps, not the two to three hours that it did take.

In adjudicating the repose claim, the court said that the statute of repose applied only to the construction and improvements of real property.  Because the plaintiff had alleged that the design installation and construction of the sewer station was at fault, the court found that these allegations were barred by the statute of repose when the design, construction and installation had occurred more than ten years prior to the filing of the lawsuit. 

The court went on to find that the statute did not protect the city from the claims that the maintenance and operation of the sewer system and the lift stations that occurred after their installation and within the ten year period were negligent.

The court cited a previous case, Prochnow v. Elpaso Golf Clib, Inc., 253 Ill. App. 3d 387, finding that while those claims that involved the design, construction, supervision, observation or management of the construction were exempt if the acts were outside of the ten year period, the persons responsible for possession or control and suppliers of the materials used in the maintenance and operation were subject to liability for reason of construction defects.

The court then went on to address the city's claim of immunity.  Holding that the statute protects only those acts of a municipality that are shown to be both an exercise of discretion and a policy determination, the court stated that acts which are ministerial are not protected.  After a discussion of the differences between policy determinations, acts of discretion, and ministerial acts, the court found that because the city's operation of the sewage system was subject to statutory and regulatory guidelines the actions were ministerial, and that there were material issues of fact concerning whether or not the city complied with those guidelines.  "Once a municipality decides to perform pubic work, the municipality must perform the public work with reasonable care and in a nonnegligent manner" (Slip Op. at 13).

The court also found that the determination of what might amount to an extraordinary sum of rainfall was not before the court and presented a question of fact for the jury.

The appellate court reversed the trial court's grant of summary judgment to the extent it was inconsistent with the appellate opinion.

Of note to design professionals and construction companies is the application of the ten year statute of repose.  Getting done with the work and getting out will start the clock running on the ten year period.  However, if follow up maintainance work is performed, that work is still potentially the subject of litigation. More importantly for many claimants is the willingness of the court to interpret the immunity statute and discern between policy, discretion, and ministerial acts.  It should not be overlooked that too often courts are willing to apply the immunity statute without adherence to the guidelines or undertaking the analysis to determine the exact nature of the act, perhaps inspections, construction, and maintenance can all be pled correctly to make certain the municipality has to explain its actions rather than simply pleading immunity.